Line 1: | Line 1: | ||
− | = Working with RFI | + | = Working with RFI Instances = |
A Request for Information (RFI) is a set of questions shared with potential suppliers to assess their ability to fulfil certain requirements to provide goods or services. The purpose of an RFI is to solicit information from potential suppliers for buying goods or services. This is done in the form of a questionnaire with specific and general answers. The information provided by prospective suppliers are used for judging their technical capabilities, financial stability, cultural compatibility and suitability for the buying requirements of the organization. It is recommended to have specific qualification criteria for prospective supplier to compete for a business requirement of the buyer. For example, Company size in terms of revenue, technical certifications, locations and so on. An RFI does not solicit any specific proposal for any purchase or pricing information. The outcome of an RFI is a rating given to the supplier based on qualification criteria set by the buyer and not awarding of business. | A Request for Information (RFI) is a set of questions shared with potential suppliers to assess their ability to fulfil certain requirements to provide goods or services. The purpose of an RFI is to solicit information from potential suppliers for buying goods or services. This is done in the form of a questionnaire with specific and general answers. The information provided by prospective suppliers are used for judging their technical capabilities, financial stability, cultural compatibility and suitability for the buying requirements of the organization. It is recommended to have specific qualification criteria for prospective supplier to compete for a business requirement of the buyer. For example, Company size in terms of revenue, technical certifications, locations and so on. An RFI does not solicit any specific proposal for any purchase or pricing information. The outcome of an RFI is a rating given to the supplier based on qualification criteria set by the buyer and not awarding of business. | ||
− | == Creating the RFI | + | == Creating the RFI Instances == |
1. '''Click''' the ''Sourcing'' tile on the ''Dashboard''. The ''Sourcing'' page opens. A list of all the RFx instances is displayed. | 1. '''Click''' the ''Sourcing'' tile on the ''Dashboard''. The ''Sourcing'' page opens. A list of all the RFx instances is displayed. | ||
Line 31: | Line 31: | ||
**''Associate Contracts'': Sourcing app allows the buyers to create contracts such as NDA, for all the suppliers selected when creating RFI. A separate contract will be created for each supplier. | **''Associate Contracts'': Sourcing app allows the buyers to create contracts such as NDA, for all the suppliers selected when creating RFI. A separate contract will be created for each supplier. | ||
**''Mandatory Contracts'': The value in this option will be populated automatically based on the value selected in the earlier option. You cannot select any value in this option if you don’t select anything in the ''Associate Contracts'' option. | **''Mandatory Contracts'': The value in this option will be populated automatically based on the value selected in the earlier option. You cannot select any value in this option if you don’t select anything in the ''Associate Contracts'' option. | ||
− | **''Prerequisite Contracts'': The Supplier can access the RFI instance only after it is in Approved state. After the Round is started, a Terms for Participation window is displayed to the supplier with an option to accept or decline. The Suppliers can access the RFI only after they sign the Prerequisite Contract after accepting the terms for participation. If the Suppliers do not sign the contracts a message is displayed by | + | **''Prerequisite Contracts'': The Supplier can access the RFI instance only after it is in Approved state. After the Round is started, a Terms for Participation window is displayed to the supplier with an option to accept or decline. The Suppliers can access the RFI only after they sign the Prerequisite Contract after accepting the terms for participation. If the Suppliers do not sign the contracts a message is displayed by ICI, along with a list of documents asking the suppliers to complete the documents before accessing the RFI.The values selected in these fields are populated on the RFI ''Details'' page under the ''Agreements'' tab. |
The values selected in these fields are populated on the RFI ''Details ''page under ''Agreements ''tab. | The values selected in these fields are populated on the RFI ''Details ''page under ''Agreements ''tab. | ||
− | <div class="image-green-border">[[File:7.10-CreateRFI-3.PNG|720px|RTENOTITLE]]</div> <div class="image-green-border"> </div> <div class="note-box">'''Note''': Selecting an Associate Contract automatically populates the values in ''Mandatory Contracts'' and ''Prerequisite Contracts''. If you do not select any values in any of the contracts, these values will be displayed as blank when you create the RFI. This will not allow you to create Bulk Agreements. </div> <div class="image-green-border"> </div> <div class="image-green-border">7. '''Click''' ''Next''. The ''Select Template'' (Step 3 of 4) page opens. This is an optional step depending upon how the application is configured. Usually there would be only one template associated with the RFI that is selected automatically. However, multiple templates can be configured in | + | <div class="image-green-border">[[File:7.10-CreateRFI-3.PNG|720px|RTENOTITLE]]</div> <div class="image-green-border"> </div> <div class="note-box">'''Note''': Selecting an Associate Contract automatically populates the values in ''Mandatory Contracts'' and ''Prerequisite Contracts''. If you do not select any values in any of the contracts, these values will be displayed as blank when you create the RFI. This will not allow you to create Bulk Agreements. </div> <div class="image-green-border"> </div> <div class="image-green-border">7. '''Click''' ''Next''. The ''Select Template'' (Step 3 of 4) page opens. This is an optional step depending upon how the application is configured. Usually there would be only one template associated with the RFI that is selected automatically. However, multiple templates can be configured in ICI as per the business requirement. </div> <div class="image-green-border"> </div> <div class="note-box">'''Note''': You can also upload your own template as per the business requirement by clicking ''Select File'' under ''Upload Template'' section and uploading the file from your computer. </div> <div class="image-green-border"> </div> <div class="image-green-border">[[File:7.10-CreateRFI-4.PNG|720px|RTENOTITLE]]</div> <div class="image-green-border"> </div> <div class="image-green-border">8. '''Click''' ''Next''. The ''Verify'' (Step 4 of 4) page opens. Verify all the information you have just entered.</div> <div class="image-green-border"> </div> <div class="image-green-border">9. '''Click''' the ''Create RFx'' button. The RFI ''Details'' page opens.</div> <div class="image-green-border">[[File:7.10-CreateRFI-VerifyPage-1.png|720px|7.10-CreateRFI-VerifyPage-1.png]]</div> <div class="image-green-border"> </div> <div class="image-green-border">[[File:7.10-CreateRFI-VerifyPage-2.png|720px|7.10-CreateRFI-VerifyPage-2.png]]</div> <div class="image-green-border"> </div> <div class="image-green-border">[[File:7.10-CreateRFI-VerifyPage-3.png|720px|7.10-CreateRFI-VerifyPage-3.png]]</div> |
| | ||
Line 83: | Line 83: | ||
4. '''Click''' the ''View Record'' icon next to the ''Question'' to view the question information. | 4. '''Click''' the ''View Record'' icon next to the ''Question'' to view the question information. | ||
− | <div class="image-green-border">[[File:7.10-RFIDetailsPage-AddQuestionnaires3.PNG|720px]]</div> | + | <div class="image-green-border">[[File:7.10-RFIDetailsPage-AddQuestionnaires3.PNG|720px|7.10-RFIDetailsPage-AddQuestionnaires3.PNG]]</div> |
5. '''Select '''the desired question. | 5. '''Select '''the desired question. | ||
6. '''Click''' ''Save''. The selected questionnaire and question (s) are added to the RFI instance. The count is updated under the ''RFI Package'' tab. | 6. '''Click''' ''Save''. The selected questionnaire and question (s) are added to the RFI instance. The count is updated under the ''RFI Package'' tab. | ||
− | <div class="image-green-border">[[File:7.10-RFIDetailsPage-Questionnaire1.PNG|720px]]</div> | + | <div class="image-green-border">[[File:7.10-RFIDetailsPage-Questionnaire1.PNG|720px|7.10-RFIDetailsPage-Questionnaire1.PNG]]</div> |
== Creating Bulk Agreements == | == Creating Bulk Agreements == | ||
− | The Sourcing App offers you a convenient way of creating bulk agreements with the suppliers, without having to move out of RFI instance that you are working on. The agreements must be already configured in | + | The Sourcing App offers you a convenient way of creating bulk agreements with the suppliers, without having to move out of RFI instance that you are working on. The agreements must be already configured in ICI. These agreements may be made mandatory for the supplier to sign before the supplier can participate in the RFI. The RFI displays all the agreements created from the RFI and they have all the agreement information. This allows the buyer to conveniently navigate between the RFI and the agreement associated with the RFI. |
To create an agreement: | To create an agreement: | ||
Line 123: | Line 123: | ||
1. '''Click''' the ''Team'' tab on the RFI ''Details'' page. The ''Add Team'' page opens in the right pane. | 1. '''Click''' the ''Team'' tab on the RFI ''Details'' page. The ''Add Team'' page opens in the right pane. | ||
− | + | <div class="image-green-border">[[File:7.10-RFIAddTeam1.png|720px|7.10-RFIAddTeam1.png]]</div> | |
2. '''Click''' the ''Add Team'' icon. The ''Select User'' window opens. <br/> 3. '''Enter''' the search term in the ''Search User'' field to search for a desired user. | 2. '''Click''' the ''Add Team'' icon. The ''Select User'' window opens. <br/> 3. '''Enter''' the search term in the ''Search User'' field to search for a desired user. | ||
− | + | <div class="image-green-border">4. '''Select''' a User from the displayed user tiles.<br/> 5. '''Select''' a Role. For example, Approver, Business Owner, Observer, etc. <br/> 6. '''Select''' or enter the Step Number if you select Approver in the Select Role field.<br/> 7. '''Enter''' a comment in the Add Note field (optional). You can see this comment under the ''Notes'' tab.<br/> 8. '''Select''' the ''Send Notification'' checkbox if you want to the user to receive a notification of the task.<br/> 9. '''Click''' ''Add''. The ''User has been added successfully'' message is displayed.<br/> [[File:7.10-RFIAddTeam2.png|720px|7.10-RFIAddTeam2.png]]</div> | |
− | 4. '''Select''' a User from the displayed user tiles.<br/> 5. '''Select''' a Role. For example, Approver, Business Owner, Observer, etc. <br/> 6. '''Select''' or enter the Step Number if you select Approver in the Select Role field.<br/> 7. '''Enter''' a comment in the Add Note field (optional). You can see this comment under the ''Notes'' tab.<br/> 8. '''Select''' the ''Send Notification'' checkbox if you want to the user to receive a notification of the task.<br/> 9. '''Click''' ''Add''. The ''User has been added successfully'' message is displayed.<br/> | + | |
− | + | ||
== Sending the RFI instance for internal approval == | == Sending the RFI instance for internal approval == | ||
Line 137: | Line 135: | ||
When all the approvers approve the RFI instance, the status changes to Approved. After the RFI is approved, the first round is created automatically only when the round start and end date is provided. | When all the approvers approve the RFI instance, the status changes to Approved. After the RFI is approved, the first round is created automatically only when the round start and end date is provided. | ||
+ | <div class="image-green-border">[[File:7.10-RFIDetailsPage-SendforApproval.PNG|720px|7.10-RFIDetailsPage-SendforApproval.PNG]]</div> <div class="image-green-border"> </div> | ||
+ | == Modifying RFI == | ||
+ | <div class="image-green-border"> | ||
+ | When RFI is ''In Modification'', buyers can: | ||
+ | <ul style="list-style-type:circle;"> | ||
+ | <li>Add new questionnaires for rounds in any status except Closed, Evaluation Started and Evaluation Closed statuses.</li> | ||
+ | <li>Add new questions to existing questionnaire for rounds in any status except Closed, Evaluation Started and Evaluation Closed statuses.</li> | ||
+ | </ul> | ||
+ | |||
+ | The buyer can add question / questionnaires to the RFI, when the ''Allow New Question During RFI phase'' flag is toggled to ''Yes''. | ||
+ | |||
+ | [[File:Q1.png|720px|Q1.png]] | ||
+ | |||
+ | '''Prerequisite:''' | ||
+ | |||
+ | RFI is created and is ''Bidding Open'' status with suppliers added. | ||
+ | |||
+ | Rounds are created. For example, five rounds are created with status such as ''Draft, Waiting For Approval, Approved, Open, Closed.'' | ||
+ | |||
+ | [[File:QQ.png|720px|QQ.png]] | ||
+ | |||
+ | The modification changes will be reflected in rounds which are in ''Draft, Waiting For Approval, Approved,'' and''Open'' status. The ''Closed'' round will remain unchanged. The table below indicates this with example. | ||
+ | |||
+ | [[File:Q3.png|720px|Q3.png]] | ||
+ | |||
+ | === Adding a new questionnaire === | ||
+ | |||
+ | 1.'''Click '''''Modify RFx'' button. The RFx status changes to ''In Modification.'' | ||
+ | |||
+ | [[File:Capture.PNG|720px|Capture.PNG]] | ||
+ | |||
+ | 2.'''Click '''+ icon next to ''Questionnaire'' on left navigation pane on RFI''Details ''page. The ''Add Questionnaire page ''opens. | ||
+ | |||
+ | [[File:Q6.png|720px|Q6.png]] | ||
+ | |||
+ | 4. '''Select''' the ''Questionnaire Name ''that you want to add. For example, ''General Insurance. ''The'' ''''Business Disaster Recovery'''''<b>and ''Travel Guidelines'' are existing ''Questionnaire Names.'' </b> | ||
+ | |||
+ | [[File:Q7.png|720px|Q7.png]] | ||
+ | |||
+ | 5.'''Click''' ''Next''. The ''Questions'' Tab opens. | ||
+ | |||
+ | [[File:Q8.png|720px|Q8.png]] | ||
+ | |||
+ | 6.'''Select''' the questions that you want to add, for example, ''What is name of company CEO?, '' ''Company Size?'' | ||
+ | |||
+ | 7.'''Click''' ''Save.'' The questions will be saved and the RFI ''Details'' page opens. | ||
+ | |||
+ | Note that count is updated for Questionnaire and Questions. | ||
+ | |||
+ | [[File:Q10.png|720px|Q10.png]] | ||
+ | |||
+ | === Adding questions to existing questionnaire === | ||
+ | |||
+ | You can add new questions to the existing questionnaire. | ||
+ | |||
+ | '''To add new questions''' | ||
+ | |||
+ | 1.'''Click '''+ icon next to ''Questionnaire'' on left navigation pane on RFI''Details ''page. The ''Add Questionnaire page ''opens. | ||
+ | |||
+ | [[File:Q10.png|720px|Q10.png]] | ||
+ | |||
+ | 2. '''Select''' the ''Questionnaire Name ''for which you want to add further questions. For example, ''General Insurance. '' | ||
+ | |||
+ | [[File:Q7.png|720px|Q7.png]] | ||
+ | |||
+ | 3.'''Click''' ''Next''. The ''Questions'' Tab opens. | ||
+ | |||
+ | [[File:Q12.png|720px|Q12.png]] | ||
+ | |||
+ | 4.'''Select''' the questions that you want to add, for example, ''Where is your company located?,'' What is your preferred location ? are 2 new questions selected. The previously added questions are: ''What is name of company CEO?'' ''Company Size?'' | ||
+ | |||
+ | 5.'''Click''' ''Save.'' The questions will be saved and the RFI ''Details'' page opens. | ||
+ | |||
+ | Note that count of questions is updated from 4 to 6. | ||
+ | |||
+ | [[File:Q13.png|720px|Q13.png]] | ||
+ | |||
+ | Once the Questionnaire and questions are added, the RFI is send for approval. | ||
+ | |||
+ | 6.'''Click''' ''Send For Approval'' on RFI ''Details ''page. The RFI status changes to ''Bidding Open. '' | ||
+ | |||
+ | ''[[File:Q14.png|720px|Q14.png]]'' | ||
+ | |||
+ | 7.'''Click '''''Round'' tab on RFx ''Details'' page, list of ''Round Name'' opens. | ||
+ | |||
+ | [[File:Q15.png|720px|Q15.png]] | ||
+ | |||
+ | 8.'''Click''' the ''View Record'' icon next to a round in ''Draft'' Status. For example, ''Round One for RFI Rotary Compressor 2''. The round ''Details'' page opens. | ||
+ | |||
+ | [[File:Q16.png|720px|Q16.png]] | ||
+ | |||
+ | Note that count of questionnaire and questions is updated. The newly added list of questionnaire and questions are available for a round that is in ''Draft'' status. | ||
+ | |||
+ | [[File:Q17.png|720px|Q17.png]] | ||
+ | |||
+ | Similarly, the rounds in ''Waiting for Approval, Approved, Open'' status, the newly added Questionnaire and questions are updated and available. (Except ''Closed'' round) | ||
+ | |||
+ | [[File:Q18.png|720px|Q18.png]] | ||
+ | |||
+ | The count of Questionnaire and questions is updated for round in ''Approved'' status. | ||
+ | |||
+ | [[File:Q19.png|720px|Q19.png]] | ||
+ | |||
+ | Similarly, the count of Questionnaire and questions is updated for round in ''Open'' status. | ||
+ | |||
+ | [[File:Q20.png|720px|Q20.png]] | ||
+ | |||
+ | Note that newly added questionnaire and questions is not updated for the round in ''Closed ''status and it remains unchanged. | ||
+ | [[File:Q21.png|720px|Q21.png]] | ||
+ | </div> | ||
== Working with Rounds == | == Working with Rounds == | ||
Line 150: | Line 258: | ||
1. '''Click '''''Round ''on the RFI ''Details ''page. The auto created round instance is displayed. | 1. '''Click '''''Round ''on the RFI ''Details ''page. The auto created round instance is displayed. | ||
<div class="note-box">'''Note''': Only the first round is created automatically. The buyers must create the other rounds manually as required. </div> | <div class="note-box">'''Note''': Only the first round is created automatically. The buyers must create the other rounds manually as required. </div> | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-StartRound1.PNG|720px|7.10-StartRound1.PNG]]</div> | ||
2. '''Click''' the ''View Record'' icon. The Round’s ''Details'' page opens with the round in ''Draft'' state. | 2. '''Click''' the ''View Record'' icon. The Round’s ''Details'' page opens with the round in ''Draft'' state. | ||
Line 161: | Line 271: | ||
1. '''Click''' the plus icon under the ''Round'' tab on the RFI ''Details'' page. The ''Create RFI -Round'' page opens. | 1. '''Click''' the plus icon under the ''Round'' tab on the RFI ''Details'' page. The ''Create RFI -Round'' page opens. | ||
− | + | <div class="image-green-border">[[File:7.10-CreateRound.png|720px|7.10-CreateRound.png]]</div> | |
2. '''Click''' the ''Organization Unit'' icon to select the Organization Unit. | 2. '''Click''' the ''Organization Unit'' icon to select the Organization Unit. | ||
Line 172: | Line 282: | ||
6. '''Select '''a ''Round End Date ''and time. | 6. '''Select '''a ''Round End Date ''and time. | ||
<div class="note-box">'''Note''': The date and time is displayed based on the user’s locale settings. When the user with different locale views the RFI, the date and time are converted to their locale.</div> | <div class="note-box">'''Note''': The date and time is displayed based on the user’s locale settings. When the user with different locale views the RFI, the date and time are converted to their locale.</div> | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-CreateRound1.PNG|720px|7.10-CreateRound1.PNG]]</div> | ||
7. '''Click''' ''Next''. The ''Select Template'' page opens. | 7. '''Click''' ''Next''. The ''Select Template'' page opens. | ||
Line 177: | Line 289: | ||
9. '''Click''' the ''Create Round'' button. The Round’s ''Details'' page opens. The round is now created in ''Draft'' state. | 9. '''Click''' the ''Create Round'' button. The Round’s ''Details'' page opens. The round is now created in ''Draft'' state. | ||
− | + | <div class="image-green-border">[[File:7.10-CreateRound4.png|720px|7.10-CreateRound4.png]]</div> | |
10. '''Click''' the ''Start Round'' button to begin the Round. The status of the round changes to ''Approved and Scheduled''. When the round is approved the status changes to ''Published''. When the current date is equal to start date of the round the status changes to ''Published''. | 10. '''Click''' the ''Start Round'' button to begin the Round. The status of the round changes to ''Approved and Scheduled''. When the round is approved the status changes to ''Published''. When the current date is equal to start date of the round the status changes to ''Published''. | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-StartRound.PNG|720px|7.10-StartRound.PNG]]</div> | ||
== Working with Questions == | == Working with Questions == | ||
Line 190: | Line 304: | ||
To submit responses: | To submit responses: | ||
− | 1. '''Click''' the ''Sourcing'' tile on the ''Dashboard'' after logging on to | + | 1. '''Click''' the ''Sourcing'' tile on the ''Dashboard'' after logging on to ICI. The ''Sourcing'' page opens. This page displays a list of all the RFI instances that the supplier is a part of. |
− | + | <div class="image-green-border">[[File:7.10-SubmitResponses1.png|720px|7.10-SubmitResponses1.png]]</div> | |
− | 2. '''Click''' the ''View Record'' icon next to the questionnaire that you want to respond to. The ''Terms For Participation'' window opens where the supplier must accept or decline them. < | + | 2. '''Click''' the ''View Record'' icon next to the questionnaire that you want to respond to. The ''Terms For Participation'' window opens where the supplier must accept or decline them. |
− | + | <div class="note-box">'''Note''': The supplier must accept the terms and conditions to participate in the RFI and provide response to buyers if they are added by the buyer when creating the RFI.</div> | |
+ | | ||
+ | <div class="image-green-border">[[File:7.10-SubmitResponses2.png|720px|7.10-SubmitResponses2.png]]</div> | ||
3. '''Click''' ''Accept'' on ''Terms For Participation'' window. The RFI ''Details'' page opens with the RFI in ''Round(s) Ongoing'' state. | 3. '''Click''' ''Accept'' on ''Terms For Participation'' window. The RFI ''Details'' page opens with the RFI in ''Round(s) Ongoing'' state. | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-SubmitResponses3.png|720px|7.10-SubmitResponses3.png]]</div> | ||
4. '''Click''' ''RFI Round'' under ''Round'' tab. The list of Rounds are displayed in the grid along with its details such as ''Round Name'', ''Round Code'' etc. | 4. '''Click''' ''RFI Round'' under ''Round'' tab. The list of Rounds are displayed in the grid along with its details such as ''Round Name'', ''Round Code'' etc. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponses4.png|720px|7.10-SubmitResponses4.png]]</div> | |
5. '''Click''' the ''View Record'' icon. The ''Round Details'' window opens. It displays the information of the questionnaire and questions given by the buyer. | 5. '''Click''' the ''View Record'' icon. The ''Round Details'' window opens. It displays the information of the questionnaire and questions given by the buyer. | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-SubmitResponses5.png|720px|7.10-SubmitResponses5.png]]</div> | ||
6. '''Click''' ''RFI Response'' on ''Round Details'' page. The list of responses is displayed. | 6. '''Click''' ''RFI Response'' on ''Round Details'' page. The list of responses is displayed. | ||
7. '''Click''' the ''View Record'' button next to the RFI Response. The ''RFI Response'' page opens. | 7. '''Click''' the ''View Record'' button next to the RFI Response. The ''RFI Response'' page opens. | ||
+ | | ||
+ | <div class="image-green-border">[[File:7.10-SubmitResponses6.png|720px|7.10-SubmitResponses6.png]]</div> | ||
8. '''Click''' plus icon next to ''Supplier Documents'' if you want to add any supporting documents when responding to the RFI. The ''Create Association'' page opens. | 8. '''Click''' plus icon next to ''Supplier Documents'' if you want to add any supporting documents when responding to the RFI. The ''Create Association'' page opens. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponses7.png|720px|7.10-SubmitResponses7.png]]</div> | |
9. '''Enter''' the information on ''Create Association'' page and then '''select''' the file from your computer. | 9. '''Enter''' the information on ''Create Association'' page and then '''select''' the file from your computer. | ||
10. '''Click''' ''Create''. The count of ''Supplier Documents'' is displayed in the left navigation pane on RFI ''Details'' page of the supplier. | 10. '''Click''' ''Create''. The count of ''Supplier Documents'' is displayed in the left navigation pane on RFI ''Details'' page of the supplier. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponses8.png|720px|7.10-SubmitResponses8.png]]</div> | |
11. '''Click''' ''RFI Question Response''. The list of questions asked by the buyer is displayed. | 11. '''Click''' ''RFI Question Response''. The list of questions asked by the buyer is displayed. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponses9.png|720px|7.10-SubmitResponses9.png]]</div> | |
You can respond to questions asked by the buyer in the following way: | You can respond to questions asked by the buyer in the following way: | ||
*Using Microsoft Excel | *Using Microsoft Excel | ||
− | *Using | + | *Using ICI |
'''Using Microsoft Excel''' | '''Using Microsoft Excel''' | ||
Line 222: | Line 344: | ||
1. '''Click''' ''Export associated document data template'' icon on the page that shows the list of questions to download the questions in an Excel sheet. | 1. '''Click''' ''Export associated document data template'' icon on the page that shows the list of questions to download the questions in an Excel sheet. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel1.png|720px|7.10-SubmitResponseusingExcel1.png]]</div> <div class="image-green-border"> </div> <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel2.png|720px|7.10-SubmitResponseusingExcel2.png]]</div> | |
2. '''Click''' ''Enable Editing'' to add the response in the Excel sheet. | 2. '''Click''' ''Enable Editing'' to add the response in the Excel sheet. | ||
Line 228: | Line 350: | ||
4. '''Click '''''Import associated document data template ''icon to upload the response excel sheet. The ''Upload Document'' window opens. | 4. '''Click '''''Import associated document data template ''icon to upload the response excel sheet. The ''Upload Document'' window opens. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel3.png|720px|7.10-SubmitResponseusingExcel3.png]]</div> | |
5. '''Click''' ''Select File'' to select the file from your computer. | 5. '''Click''' ''Select File'' to select the file from your computer. | ||
Line 236: | Line 358: | ||
8. '''Click''' ''Submit''. The ''Please Confirm'' window opens. | 8. '''Click''' ''Submit''. The ''Please Confirm'' window opens. | ||
− | + | <div class="note-box">'''Note''': You should click on submit only after you have entered values for all items. </div> | |
− | '''Note''': You should click on submit only after you have entered values for all items. | + | |
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel4.png|720px|7.10-SubmitResponseusingExcel4.png]]</div> | |
9. '''Click''' ''Yes''. The status of RFI response changes to ''Submitted''. | 9. '''Click''' ''Yes''. The status of RFI response changes to ''Submitted''. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel5.png|720px|7.10-SubmitResponseusingExcel5.png]]</div> <div class="image-green-border"> </div> <div class="image-green-border">[[File:7.10-SubmitResponseusingExcel6.png|720px|7.10-SubmitResponseusingExcel6.png]]</div> | |
After submitting responses, suppliers cannot edit them. To edit the responses, suppliers must '''click''' ''Withdraw''. This changes the status of the Questionnaire to Withdrawn. Suppliers can revert withdrawal by clicking ''Revert Withdrawal''. | After submitting responses, suppliers cannot edit them. To edit the responses, suppliers must '''click''' ''Withdraw''. This changes the status of the Questionnaire to Withdrawn. Suppliers can revert withdrawal by clicking ''Revert Withdrawal''. | ||
Line 246: | Line 368: | ||
1. '''Click''' ''Withdraw'' on the RFI Response ''Details'' page. The ''Please Confirm'' window opens. | 1. '''Click''' ''Withdraw'' on the RFI Response ''Details'' page. The ''Please Confirm'' window opens. | ||
− | + | <div class="image-green-border">[[File:7.10-WithdrawResponse1.png|720px|7.10-WithdrawResponse1.png]]</div> | |
2. '''Click''' ''Yes'' to withdraw the response. The ''Add Note'' window opens. | 2. '''Click''' ''Yes'' to withdraw the response. The ''Add Note'' window opens. | ||
− | + | <div class="image-green-border">[[File:7.10-WithdrawResponse2.png|720px|7.10-WithdrawResponse2.png]]</div> | |
3. '''Select''' the reason code from the drop-down or enter the text stating the reason for withdrawing the response and '''click''' ''Add''. | 3. '''Select''' the reason code from the drop-down or enter the text stating the reason for withdrawing the response and '''click''' ''Add''. | ||
− | + | <div class="image-green-border">[[File:7.10-WithdrawResponse3.png|720px|7.10-WithdrawResponse3.png]]</div> | |
The status of RFI Response changes to ''Withdrawn.'' | The status of RFI Response changes to ''Withdrawn.'' | ||
You can revert withdrawal by clicking ''Revert Withdraw''. The status of the RFI Response changes to ''Draft.'' | You can revert withdrawal by clicking ''Revert Withdraw''. The status of the RFI Response changes to ''Draft.'' | ||
+ | <div class="image-green-border">''[[File:7.10-RevertWithdraw1.png|720px|7.10-RevertWithdraw1.png]]''</div> | ||
+ | '''Using ICI''' | ||
− | + | To submit responses using ICI: | |
− | + | ||
− | To submit responses using | + | |
1. '''Click''' ''RFI Question Response'' on RFI Response ''Details'' page. The list of questions are displayed in the right pane of the page. | 1. '''Click''' ''RFI Question Response'' on RFI Response ''Details'' page. The list of questions are displayed in the right pane of the page. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingICM1.png|720px|7.10-SubmitResponseusingICM1.png]]</div> | |
2. '''Click''' ''Edit'' icon next to the question for which you want to respond. The page displaying the question and response you want to provide opens. | 2. '''Click''' ''Edit'' icon next to the question for which you want to respond. The page displaying the question and response you want to provide opens. | ||
3. '''Enter''' the response in Question Response field and '''click''' ''Update''. The RFI Question Response ''Details'' opens. | 3. '''Enter''' the response in Question Response field and '''click''' ''Update''. The RFI Question Response ''Details'' opens. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingICM2.png|720px|7.10-SubmitResponseusingICM2.png]]</div> | |
4. '''Click''' ''Go to Parent Agreement''. The RFI Response ''Details'' page opens. | 4. '''Click''' ''Go to Parent Agreement''. The RFI Response ''Details'' page opens. | ||
5. '''Click''' ''Submit''. Repeat the same steps from Using Microsoft Excel section to submit and withdraw the responses. | 5. '''Click''' ''Submit''. Repeat the same steps from Using Microsoft Excel section to submit and withdraw the responses. | ||
− | + | <div class="image-green-border">[[File:7.10-SubmitResponseusingICM3.png|720px|7.10-SubmitResponseusingICM3.png]]</div> | |
=== Response Analysis === | === Response Analysis === | ||
Line 278: | Line 400: | ||
2. '''Open''' the excel sheet. You can view the all the data collected from the supplier responses such as ''Supplier ID'', ''Item Name'', ''Item Description'', etc. | 2. '''Open''' the excel sheet. You can view the all the data collected from the supplier responses such as ''Supplier ID'', ''Item Name'', ''Item Description'', etc. | ||
+ | <div class="image-green-border">[[File:7.10-ViewResponsesinExcel.png|720px|7.10-ViewResponsesinExcel.png]]</div> <div class="image-green-border"> </div> <div class="image-green-border"> </div> <div class="image-green-border"> </div> <div class="image-green-border"> </div> <div class="image-green-border"> </div> <div class="image-green-border">'''Related Topics''':'' [[Agreement_Management|Agreement Management]] | [[ICI_Sourcing_App|ICI Sourcing App]]| [[Working_with_RFx|Working with RFx]] | [[Obligation_Management|Obligation Management]] |''</div> |
Latest revision as of 06:45, 12 September 2020
Contents
Working with RFI Instances
A Request for Information (RFI) is a set of questions shared with potential suppliers to assess their ability to fulfil certain requirements to provide goods or services. The purpose of an RFI is to solicit information from potential suppliers for buying goods or services. This is done in the form of a questionnaire with specific and general answers. The information provided by prospective suppliers are used for judging their technical capabilities, financial stability, cultural compatibility and suitability for the buying requirements of the organization. It is recommended to have specific qualification criteria for prospective supplier to compete for a business requirement of the buyer. For example, Company size in terms of revenue, technical certifications, locations and so on. An RFI does not solicit any specific proposal for any purchase or pricing information. The outcome of an RFI is a rating given to the supplier based on qualification criteria set by the buyer and not awarding of business.
Creating the RFI Instances
1. Click the Sourcing tile on the Dashboard. The Sourcing page opens. A list of all the RFx instances is displayed.
2. Click the Create RFx tile. The Create RFx page opens.
3. Select a Sourcing Entity from the Select Sourcing Entity drop-down in the Contract Type Details (Step 1 of 4) section. The contract type is configured in the system with default Attributes.
4. Click Next. The Attributes (Step 2 of 4) page opens. The attributes are grouped under various categories. For example, RFI Information, RFI Configuration, etc.
5. Select or enter the values for all the required Attributes in the RFI Information group:
- Enter the RFI Name. For example, Laptop Supplier Information.
- Enter the information of the RFI instance in the Description field.
- Select the Round One Start Date and Round One End Date. When you enter the dates, a round is created automatically as soon as the RFI instance is approved. If the round start and end dates are not provided, the round will not be created for the RFI instance.
6. Select appropriate values and settings under the RFI Configuration group.
- Select Yes or No for the following Configuration settings as per your requirement:
- Allow Foreclosure of Rounds: Select Yes if you want to allow closing the round before the selected round end date. This displays the Close Round button on the Round Details page to close the round manually before scheduled Round end date and time.If you select No, then the round will be closed automatically at the selected round end date and time. The default value for this option is set to Yes.
- Copy Questions and Supplier Responses from previous Round: Select Yes if you want to allow copying questions and supplier responses from previous rounds to the new round. The default value for this option is set to Yes.
- Allow new supplier during RFI phase: Select Yes if you want to allow adding a new supplier(s) during the entire RFI lifecycle. However, the newly added supplier(s) can participate in a new round only, not in an ongoing round. The default value for this option is set to Yes.
- Allow new question during RFI phase: Select Yes if you want to allow adding a new question during the RFI lifecycle. However the newly added question (s) can be part of the round only before it starts and not in an ongoing round. The default value for this option is set to Yes.
- Enter the Terms For Participation in the given field. This window will be visible to the suppliers only if the buyer adds the terms for participation when creating the RFI. The suppliers should accept the Terms before they can respond to the questions asked by the buyer. The Supplier can access the RFI instance only after it is in Approved state. After the Round is started, a Terms for Participation window is displayed to the supplier with an option to accept or decline. For example, if a supplier has multiple contacts and if one of the contacts accepts the terms for participation, then other contacts are not required to take any action on that and the Terms for Participation will not be displayed to the remaining contacts.
- Select the following contracts (if applicable) by clicking the drop-down arrow or the Lookup Search icon:
- Associate Contracts: Sourcing app allows the buyers to create contracts such as NDA, for all the suppliers selected when creating RFI. A separate contract will be created for each supplier.
- Mandatory Contracts: The value in this option will be populated automatically based on the value selected in the earlier option. You cannot select any value in this option if you don’t select anything in the Associate Contracts option.
- Prerequisite Contracts: The Supplier can access the RFI instance only after it is in Approved state. After the Round is started, a Terms for Participation window is displayed to the supplier with an option to accept or decline. The Suppliers can access the RFI only after they sign the Prerequisite Contract after accepting the terms for participation. If the Suppliers do not sign the contracts a message is displayed by ICI, along with a list of documents asking the suppliers to complete the documents before accessing the RFI.The values selected in these fields are populated on the RFI Details page under the Agreements tab.
The values selected in these fields are populated on the RFI Details page under Agreements tab.
RFI Details page
Buyers can view the current status and details of the RFI. Buyers can also perform a variety of actions based on the current state of the RFI.
Here is a brief description of the options in the left navigation pane of RFI Details page.
- RFI Information: This section displays the basic details of the current RFI instance. It has the following sub-sections.
- Summary: Displays the name of the RFI instance (that is added while creating) and who created it, and RFI instance details.
- Details: Displays the details specified while creating the RFI instance.
- Preview: Displays how the RFI document would actually look. Click the click here in To see full document click here to download and view the full document in pdf format.
- RFI Package: This section displays the following details.
- Questionnaire: Click this option to view the list of questionnaires associated with the RFI. Click the plus icon next to Questionnaire on RFI Details page to add a new questionnaire. You can select or remove questionnaire from the available list of questionnaires. It is mandatory to add a questionnaire along with questions to the RFI before sending the RFI for approval.
- Question: Click this option to view the list of questions associated with the questionnaire and RFI.
- Internal Attachments: Displays the list of existing internal attachments associated with the RFI. Internal attachments are associated documents uploaded by the buyers and only available to the buyer team. Click the plus icon next to internal attachments to add new to the list.
- External Attachments: Displays the list of existing external attachments associated with the RFI. External attachments are associated documents uploaded by the buyers and available to both buyers and suppliers. Click the plus icon next to external attachments to add new to the list. For example, the bulk agreements such as NDA and Warranty agreements are displayed under this section.
- Supplier Information: Displays the list of existing suppliers and allows buyers to add new suppliers along with their contact information.
- Suppliers: Displays the list of suppliers added to the RFI created by the buyer. Click the plus icon next to Suppliers to add a new supplier.
- Supplier Contacts: Displays the list of relevant supplier contacts that are populated automatically after you select the suppliers in the previous step.
- Agreements: Displays all the agreements that were selected initially when creating the RFI.
- Collaboration: Allows the internal or external team members to communicate with other internal or external team members by creating topics and posting messages in it.
- Round: Displays the list of rounds (automatic and manual) associated with the RFI along with their current state. Click the plus icon next to Round to add a new round.
- Team: Displays the members added to the team for this RFI instance. Click the plus icon to add new team members to the RFI.
- Notes: Displays the additional information about the RFI if it is added.
- History: Displays how the RFI has progressed till now. The actions performed by the buyer are displayed by the buyer and supplier on the RFI instance are displayed under History in the left navigation pane on RFI Details page.
Buyers can perform the following actions from the RFI Details page:
- Download RFI Document: Click this button to download the RFI document in Microsoft Word format. The downloaded document is based on the template selected while creating the RFI instance.
- Edit: Click this button to go back and make changes to the RFI that you created.
- Send for Approval: Click this button to send the RFI instance for approval.
- Download Package: Click this button to download the RFI instance along with all its associations. You can select specific associations that you want to download or select the RFI instance checkbox to download the RFI package. RFI package is downloaded as a zip file that contains all the attachments relevant to the RFI. When the zip file is exported on user’s local machine, a folder structure is created that resembles the RFI structure, and the files are located in the respective locations.
- Delete: Click this button to delete the RFI instance. After deleting the RFI instance, the Sourcing page opens and the deleted RFI will not be available on the user interface.
Adding Questionnaires
You can add questionnaires at any stage of the RFI instance depending upon RFI configuration settings. Questionnaires are a set of questions that the buyer shares with potential suppliers who can fulfil the requirement of providing goods or services to the buyers. When you create the RFI instance, the RFI Details page opens with the RFI status displayed as Draft. You can use the left navigation pane to add one or more questionnaires.
To add questionnaires:
1. Click the plus button next to Questionnaire under the RFI Package tab. The Questionnaires window opens.
2. Search for the desired questionnaire (s) or select the questionnaire from the displayed list under the Questionnaires tab.
3. Click Next. The Questions tab opens displaying the list of questions associated with the questionnaire.
4. Click the View Record icon next to the Question to view the question information.
5. Select the desired question.
6. Click Save. The selected questionnaire and question (s) are added to the RFI instance. The count is updated under the RFI Package tab.
Creating Bulk Agreements
The Sourcing App offers you a convenient way of creating bulk agreements with the suppliers, without having to move out of RFI instance that you are working on. The agreements must be already configured in ICI. These agreements may be made mandatory for the supplier to sign before the supplier can participate in the RFI. The RFI displays all the agreements created from the RFI and they have all the agreement information. This allows the buyer to conveniently navigate between the RFI and the agreement associated with the RFI.
To create an agreement:
1. Click the Create Association icon next to the agreements in the left navigation pane on the RFI Details page. For example, NDA, Warranty Agreement.
3. Enter values for all the attributes, some of which may be mandatory.
4. Click the Select Multiple Suppliers icon next to Suppliers and Agreement Details. The Supplier page opens.
5. Repeat steps 2 to 6 from the Selecting Suppliers section to add a supplier.
6. Click Next. The Select Template (Step 3 of 4) page opens.
7. Select a Template.
8. Click Next. The Verify page opens. Verify all the information you have entered.
9. Click the Bulk Create Agreement button. The agreement is created.
10. Click the View Record icon next to the NDA instance on the Sourcing page. The NDA’s Details page opens with the NDA in the Draft state.
After the Agreement is created for a supplier, you can proceed with the agreement workflow as configured. For example, you can send the agreement for approval.
11. Click the Send For External Signature button on the Details page. The agreement is sent to the supplier(s) for signatures. The status of the agreement changes to Executed when all the suppliers sign the NDA.
Adding Team members in RFI
A team of Approvers, Reviewers, and Observers can be added to the RFI instance for completing the workflow.
To add team members:
1. Click the Team tab on the RFI Details page. The Add Team page opens in the right pane.
2. Click the Add Team icon. The Select User window opens.
3. Enter the search term in the Search User field to search for a desired user.
5. Select a Role. For example, Approver, Business Owner, Observer, etc.
6. Select or enter the Step Number if you select Approver in the Select Role field.
7. Enter a comment in the Add Note field (optional). You can see this comment under the Notes tab.
8. Select the Send Notification checkbox if you want to the user to receive a notification of the task.
9. Click Add. The User has been added successfully message is displayed.
Sending the RFI instance for internal approval
The RFI instance must be in Approved state before a round is created automatically and the RFI workflow can be completed.
1. Click the Send For Approval button on the RFIDetails page. The RFI instance is sent for approval to the approver(s) you have selected in the Team.
The status changes to Waiting for Approval. A task is created for each approver.
When all the approvers approve the RFI instance, the status changes to Approved. After the RFI is approved, the first round is created automatically only when the round start and end date is provided.
Modifying RFI
When RFI is In Modification, buyers can:
- Add new questionnaires for rounds in any status except Closed, Evaluation Started and Evaluation Closed statuses.
- Add new questions to existing questionnaire for rounds in any status except Closed, Evaluation Started and Evaluation Closed statuses.
The buyer can add question / questionnaires to the RFI, when the Allow New Question During RFI phase flag is toggled to Yes.
Prerequisite:
RFI is created and is Bidding Open status with suppliers added.
Rounds are created. For example, five rounds are created with status such as Draft, Waiting For Approval, Approved, Open, Closed.
The modification changes will be reflected in rounds which are in Draft, Waiting For Approval, Approved, andOpen status. The Closed round will remain unchanged. The table below indicates this with example.
Adding a new questionnaire
1.Click Modify RFx button. The RFx status changes to In Modification.
2.Click + icon next to Questionnaire on left navigation pane on RFIDetails page. The Add Questionnaire page opens.
4. Select the Questionnaire Name that you want to add. For example, General Insurance. The 'Business Disaster Recoveryand Travel Guidelines are existing Questionnaire Names.
5.Click Next. The Questions Tab opens.
6.Select the questions that you want to add, for example, What is name of company CEO?, Company Size?
7.Click Save. The questions will be saved and the RFI Details page opens.
Note that count is updated for Questionnaire and Questions.
Adding questions to existing questionnaire
You can add new questions to the existing questionnaire.
To add new questions
1.Click + icon next to Questionnaire on left navigation pane on RFIDetails page. The Add Questionnaire page opens.
2. Select the Questionnaire Name for which you want to add further questions. For example, General Insurance.
3.Click Next. The Questions Tab opens.
4.Select the questions that you want to add, for example, Where is your company located?, What is your preferred location ? are 2 new questions selected. The previously added questions are: What is name of company CEO? Company Size?
5.Click Save. The questions will be saved and the RFI Details page opens.
Note that count of questions is updated from 4 to 6.
Once the Questionnaire and questions are added, the RFI is send for approval.
6.Click Send For Approval on RFI Details page. The RFI status changes to Bidding Open.
7.Click Round tab on RFx Details page, list of Round Name opens.
8.Click the View Record icon next to a round in Draft Status. For example, Round One for RFI Rotary Compressor 2. The round Details page opens.
Note that count of questionnaire and questions is updated. The newly added list of questionnaire and questions are available for a round that is in Draft status.
Similarly, the rounds in Waiting for Approval, Approved, Open status, the newly added Questionnaire and questions are updated and available. (Except Closed round)
The count of Questionnaire and questions is updated for round in Approved status.
Similarly, the count of Questionnaire and questions is updated for round in Open status.
Note that newly added questionnaire and questions is not updated for the round in Closed status and it remains unchanged.
Working with Rounds
One cycle of seeking responses from suppliers and evaluating them is referred to as a round. A complete Sourcing event may comprise of multiple rounds. The first round is created automatically (if the start and end dates are entered) as soon as the RFI instance is approved. You can see the round on the RFI Details page. You must open the round instance and fill in additional details. There can be multiple rounds for a single RFI instance.
Starting the scheduled Rounds
You can schedule a round by entering the Round Start Date and End Date when creating the RFI instance. The buyer must click the Start Round button on the Round Details page to start the round.
To start the round:
1. Click Round on the RFI Details page. The auto created round instance is displayed.
2. Click the View Record icon. The Round’s Details page opens with the round in Draft state.
3. Click the Start Round button to start the Round. The status of RFI changes to Round(s) Ongoing after the round is approved and published.
Creating Rounds
The buyer can also create a round manually if they need to conduct multiple rounds with the supplier. The buyer can create the round manually only if the RFI instance is in Approved, Round(s) Ongoing and Round (s) Closed state.
To create a round (manually):
1. Click the plus icon under the Round tab on the RFI Details page. The Create RFI -Round page opens.
2. Click the Organization Unit icon to select the Organization Unit.
3. Enter an appropriate name for the round.
4. Enter relevant details in the Description field.
5. Select a Round Start Date. This field is already populated with the current date. You can select a different date and time if required.
6. Select a Round End Date and time.
7. Click Next. The Select Template page opens.
8. Select the Template from the available list or upload a new template from your computer and click Next. The Verify page opens. Verify all the information.
9. Click the Create Round button. The Round’s Details page opens. The round is now created in Draft state.
10. Click the Start Round button to begin the Round. The status of the round changes to Approved and Scheduled. When the round is approved the status changes to Published. When the current date is equal to start date of the round the status changes to Published.
Working with Questions
A question is the information asked by buyers about the products or services that they want to buy to the prospective suppliers before purchasing them. The supplier can view the questions that were submitted in the previous rounds if the buyer selects Yes in the Copy Questions and Supplier Responses option when creating the RFI.
Depending upon how the RFI instance is configured in the organization, suppliers must sign all the prerequisite agreements before submitting the responses to the questions asked by buyers. The suppliers won’t be able to view the RFI instance until the prerequisite agreement is in Executed state.
Submitting Responses
Supplier can upload, edit and then submit the responses for the questions.
To submit responses:
1. Click the Sourcing tile on the Dashboard after logging on to ICI. The Sourcing page opens. This page displays a list of all the RFI instances that the supplier is a part of.
2. Click the View Record icon next to the questionnaire that you want to respond to. The Terms For Participation window opens where the supplier must accept or decline them.
3. Click Accept on Terms For Participation window. The RFI Details page opens with the RFI in Round(s) Ongoing state.
4. Click RFI Round under Round tab. The list of Rounds are displayed in the grid along with its details such as Round Name, Round Code etc.
5. Click the View Record icon. The Round Details window opens. It displays the information of the questionnaire and questions given by the buyer.
6. Click RFI Response on Round Details page. The list of responses is displayed.
7. Click the View Record button next to the RFI Response. The RFI Response page opens.
8. Click plus icon next to Supplier Documents if you want to add any supporting documents when responding to the RFI. The Create Association page opens.
9. Enter the information on Create Association page and then select the file from your computer.
10. Click Create. The count of Supplier Documents is displayed in the left navigation pane on RFI Details page of the supplier.
11. Click RFI Question Response. The list of questions asked by the buyer is displayed.
You can respond to questions asked by the buyer in the following way:
- Using Microsoft Excel
- Using ICI
Using Microsoft Excel
To submit responses using Excel:
1. Click Export associated document data template icon on the page that shows the list of questions to download the questions in an Excel sheet.
2. Click Enable Editing to add the response in the Excel sheet.
3. Enter the responses in the Response column and save the Excel sheet.
4. Click Import associated document data template icon to upload the response excel sheet. The Upload Document window opens.
5. Click Select File to select the file from your computer.
6. Click Upload File to upload the file. The Upload Summary is displayed showing the number of records that were processed successfully, deleted and failed records.
7. Click Ok. The RFI Response page opens.
8. Click Submit. The Please Confirm window opens.
9. Click Yes. The status of RFI response changes to Submitted.
After submitting responses, suppliers cannot edit them. To edit the responses, suppliers must click Withdraw. This changes the status of the Questionnaire to Withdrawn. Suppliers can revert withdrawal by clicking Revert Withdrawal.
To withdraw the response:
1. Click Withdraw on the RFI Response Details page. The Please Confirm window opens.
2. Click Yes to withdraw the response. The Add Note window opens.
3. Select the reason code from the drop-down or enter the text stating the reason for withdrawing the response and click Add.
The status of RFI Response changes to Withdrawn.
You can revert withdrawal by clicking Revert Withdraw. The status of the RFI Response changes to Draft.
Using ICI
To submit responses using ICI:
1. Click RFI Question Response on RFI Response Details page. The list of questions are displayed in the right pane of the page.
2. Click Edit icon next to the question for which you want to respond. The page displaying the question and response you want to provide opens.
3. Enter the response in Question Response field and click Update. The RFI Question Response Details opens.
4. Click Go to Parent Agreement. The RFI Response Details page opens.
5. Click Submit. Repeat the same steps from Using Microsoft Excel section to submit and withdraw the responses.
Response Analysis
It is the process of analyzing supplier responses with an intent to compare one against the others along the evaluation criteria. When all the desired Responses are received, you can view and analyze all the responses to be able to take informed decision.
At least one round should be completed for conducting response analysis, otherwise the user gets an error message indicating that the round must be started to download response analysis.
To analyze supplier response:
1. Click the Download Response Analysis button on the RFI Details page. An excel sheet containing the question responses is downloaded.
2. Open the excel sheet. You can view the all the data collected from the supplier responses such as Supplier ID, Item Name, Item Description, etc.